The Hydrocarbon Pollution Remediation Project (HYPREP) is this year drawing from a new policy thrust that prioritises timely completion of all projects within stated timelines.
The Project Coordinator of HYPREP, Prof Nenibarini Zabbey, who gave the indication during the Project’s 2025 first quarter interactive session with Ogoni youths in Port Harcourt, said as a community-based project, HYPREP understands the urgency of protecting the environment and improving livelihoods in line with its mandate.
He disclosed that the Centre of Excellence for Environmental Restoration(CEER) for example, is currently being painted, as part of its final finishing works, stressing that HYPREP is ensuring that the centre is commissioned this year for public use.
According to him, the Technical Planning Committee for CEER had submitted its report which contains various recommendations for the operationalisation of the centre.
He further disclosed that the shoreline remediation project is at a completion rate of 39.4 percent, saying, HYPREP has in this area recovered, evaluated and treated over 937,000 litres of oily sludge from the mangrove sediment, as well as evacuated over 1.7million kilogrammes of solid waste from the Ogoni creeks.
According to him, the mangrove restoration project has reached 86 percent completion rate, while the monitoring of the planted mangrove grids is progressing well, adding that HYPREP has also initiated a practical framework for long-term monitoring to ensure the Project’s objectives are met.
The Project Coordinator said HYPREP has achieved significant milestones in the ongoing construction of new water facilities in Ogoni communities, stressing that it is determined to commission the new water facilities in the various communities in the third quarter of this year.
He assured the participants that HYPREP would commission water facilities every two months in Ogoni communities and announced that the Creative Arts training for more Ogoni youths would begin in the second quarter of the year, while other array of interventions to support small and medium scale businesses would be rolled out in the coming weeks.
He revealed that the construction of the Ogoni Specialist Hospital has advanced to a completion rate of 70 percent, while that of Buan Cottage Hospital has reached 93.8 percent.
He also disclosed that in March, the Project Coordination Office took delivery of the first batch of equipment and electrical parts for the Ogoni Power Project, and expects further deliveries in this second quarter.
Zabbey said HYPREP has also deepened its engagement with critical stakeholders, including Ogoni youths and women, adding that this periodic interactive session remains a key part of its yearly work plan to ensure that their voices are heard.
He hinted that some selected youth leaders would benefit from the second batch of the Ogoni traditional rulers and other key stakeholders workshop on mechanism for alternative dispute resolution.
At the interactive session, Dr Sorbarikor Lebura of the Rivers State University delivered a keynote address on how to be on the right side of history, and encouraged Ogoni youths to always strive to be on the right side of history through their actions.
On her part, HYPREP’s Head of Sustainable Livelihood, Mrs Josephine Nzidee told the participants that the project is working hard to close out on the training of 5,000 Ogoni youths and women by ensuring that all trainees get their starter packs.
She assured persons living with disabilities in particular, that HYPREP would provide more empowerment opportunities to them.
Also, Mr Lucky Ikue announced that the Terebor water scheme, which had been out of use for some time now, due to technical glitches, would be functional soon, as the station manager has been relieved of his duties.